Public Works
Ongoing Projects
2022 Street RehabilitationThe City’s contractor, Bituminous Roadways, is making great progress on this year’s street project. Last week, the following streets were milled and re-paved:
- Barry Avenue North
- Chicago Avenue North
- Gardner Street East
- Minnetonka Avenue North
- Park Street East
- Walker Avenue North
New concrete curbs and paving were installed on Central Avenue South and on Lake Street East in the last two weeks. Repairs to irrigation systems and driveways, and turf restoration are scheduled to occur during the week of October 17
.Construction is expected to be complete by the end of October.
Verizon Wireless Installing Small-Cell EquipmentVerizon Wireless will be installing small-cell wireless antenna equipment on several City-owned street light poles on Lake Street. Contact the City’s Engineering Department at 952-404-5371 with questions related to the Verizon Wireless equipment.